Aluminum Mill Finishing Mill
Control Replacement

IPACT received an order to replace the finishing mill control system on a
three stand aluminum hot rolling mill in South Korea. The control system
consisted of
-
high speed hydraulic cylinder
control
-
screwdown control
-
inter-stand tension control
-
positive and negative roll bending
-
automatic gauge control
-
adaptive threading
-
metal-in-stand
-
mill zeroing
-
mill setup
-
modulus curve generation
-
process data collection
-
tailout and threading control.
The system
had to be fully tested with simulation, including the integration with the
mill level 2 computer and existing PLCs and HMIs. The new control was to be
installed during a planned 6 day outage.
The system
was developed and 100 percent simulated at IPACT’s facility in Valparaiso,
Indiana. Because of the simulation methodology used by IPACT, we
were able to
successfully commission the new system during the six day outage, allowing
the facility to start up as planned. Complete commissioning with fine
tuning and field requested changes totaled three weeks, during which time
the hot mill moved up the planned learning curve and back to 100 percent
production level. Due to cabinet and wiring considerations, the old
system hardware was completely demolished during
the outage, hence doing a shadowed "phase-in"
approach was not an option. The simulation allowed
the software to work successfully on the first coil through the mill.

The project
went in on time and on budget, and after the outage the system came up as
planned, with no major delays or problems. It has been functioning within
its specifications since that time,and has achieved and
outstanding 30 percent increase in productivity. The project is acknowledged by all who
were involved as a success. And it was accomplished with the implementation
being done many thousands of miles away, and commissioned on a single mill
outage. IPACT had only one opportunity and had to “get it right the first
time”.
The system
was tested using a variety of simulation techniques. Some parts of the
simulation run at extremely high speed in order to simulate such things as
cylinder positions and roll forces. Others run more slowly to simulate mill
sequencing. Because of IPACT’s hardware resources,
we were able to stage
the VME Control target, the GE 90/70 sequencing PLC, and the supervisory
OpenVMS Alpha system as part of the simulation and testing. Running the
integrated system against a simulation provides a level of testing that is
unsurpassed and our commissioning record for these systems bears that out.
The actual
control system was implemented using VMICs I/OWorks with two target VME
processors. Changes were made in the GE 90/70 mill sequencing to
accommodate the new control system. The VME, GE 90/70, and the OpenVMS
Alpha were all integrated using VMIC’s reflective memory ring. An IPACT
finishing mill setup model running in the OpenVMS supervisory system
provided the mill setup using the reflective memory ring to the GE 90/70 and
the AGC system. Feedback data received through the reflective memory from
the AGC system was used to train the finishing mill setup model. It was
also used to create a gauge report (gauge average and standard deviation per
meter of strip).
Products
GE FANUC Reflective memory
GE 90/70 PLC
Alpha OpenVMS
VMIC IOWorks
|